Licence No.: 2487
Licence Issued: October 30, 2000
IN ACCORDANCE WITH THE MANITOBA ENVIRONMENT ACT (C.C.S.M. c. E125)
THIS LICENCE IS ISSUED PURSUANT TO SECTION 11(1) TO:
MINNEDOSA COUNTRY CLUB; "the Licencee"
for the construction and operation of the Development being a nine hole expansion to
the existing nine hole golf course located on adjacent lands south of the existing
facility in the Town of Minnedosa and in accordance with the Proposal filed under The
Environment Act dated July 17, 2000 and subject to the following specifications, limits,
terms and conditions:
GENERAL TERMS AND CONDITIONS
This Section of the Licence contains requirements intended to provide guidance to the
Licencee in implementing practices to ensure that the environment is maintained in such a
manner as to sustain a high quality of life, including social and economic development,
recreation and leisure for present and future Manitobans.
- The Licencee shall, during construction, ensure that any fuel storage areas established
for the construction of the Development are located a minimum distance of 100 meters away
from waterbodies including wetlands and ensure the storage areas comply with the
requirements of Manitoba Regulation 97/88R - Storage and Handling of Gasoline and
Associated Products.
- The Licencee shall ensure that all used petroleum products and other hazardous wastes
generated by the machinery used in the construction and operation of the Development are
collected and disposed of in accordance with Manitoba Conservation and legislative
requirements.
- The Licencee shall, during the full term of the construction of the Development, cleanup
and deposit all debris from the construction site at a Waste Disposal Ground operating
under the authority of a permit issued pursuant to Manitoba Regulation 150/91 respecting
Waste Disposal Grounds.
- The Licencee shall, prior to construction, provide a copy of this Licence to the
contractor and subcontractor(s) involved in the Development.
SPECIFICATIONS, LIMITS, TERMS AND CONDITIONS
- The Licencee shall, prior to construction, instruct the on-site project construction
supervisor to arrange a meeting with representatives of the Manitoba Department of
Conservation Brandon Office and reach an agreement regarding:
- the types and locations of plantings of native species or their cultivars within
disturbed areas of the Development in order to maximize the benefit to the site and the
local ecology; and
- the adoption of a "no feeding "policy for Canada geese on the Development
property.
- The Licencee shall ensure that Little Saskatchewan River irrigation intake(s) are
screened at all times when the intake structure(s) are in the stream flow in accordance
with the procedures described in "A Fish Screening Guide for Water Intakes"
published by Fisheries and Oceans Canada. Prior to the installation of new or modified
irrigation intakes for the Development, the Licencee shall consult with representatives of
the Department of Fisheries and Oceans and reach an agreement with regard to screen size,
screen material, location of intakes and construction methods.
- The Licencee shall, where feasible, establish treed areas along the east side of the
13th fairway and along the south side of the 14th fairway to provide a buffer for future
adjacent residential development.
- The Licencee shall, from spring breakup to June 15 of each year during construction,
cease all construction activities that may impact upon the Little Saskatchewan River
stream channel and which may affect fish mobility and fish habitat.
- The Licencee shall, prior to operation of the Development, obtain a Water Rights Act
Licence for any additional water withdrawal requirements associated with the Development.
The rate of withdrawal shall not exceed 10% of the instantaneous flow of the Little
Saskatchewan River.
- The Licencee shall obtain an annual Pesticide Use Permit pursuant to Manitoba
Regulation 94/88R for the storage, handling and application of pesticides in
conjunction with the golf course operation.
- The Licencee shall not use any mercury based fungicides or Diazinon on the Development.
- The Licencee shall not:
- apply pesticides within 5 meters of the high water level of the Little Saskatchewan
River; or
- apply pesticides between 5 and 20 meters of the high water level of the little
Saskatchewan River, other than hand spot spraying.
- The Licencee shall locate a pesticide storage facility in a dry, well ventilated
separate building in an area that shall not flood and shall contain runoff from the
complete pesticide storage area. The pesticide storage facility shall be enclosed with a
security fence.
REVIEW AND REVOCATION
- If, in the opinion of the Director, the Licencee has exceeded or is exceeding or has or
is failing to meet the specifications, limits, terms, or conditions set out in this
Licence, the Director may, temporarily or permanently, revoke this Licence.
- If the construction of the Development has not commenced within three years of the date
of this Licence, the Licence is revoked.
- If, in the opinion of the Director, new evidence warrants a change in the
specifications, limits, terms or conditions of this Licence, the Director may require the
filing of a new proposal pursuant to Section 11 of The Environment Act.
"original signed by"
Larry Strachan, P. Eng.
Director
Environment Act
Client File No.: 4541.00