Header Side Menu Content Footer
Government of Manitoba
Flood Information

Lake St. Martin Emergency Channel Update

November 22, 2011

  • Water is now flowing the entire length of the channel into the Buffalo Marsh, Big Buffalo Lake and into Buffalo Creek.
  • Exploratory work for possible channel locations started July 4.
  • Logistical work such as setting up camps, building an access road and establishing drainage started in early July and additional contractors began work Aug. 15.
  • Actual channel digging started Aug. 29.
  • More than 130 workers have been involved in this construction project. At times, the Aboriginal worker complement was up to 50 per cent.
  • The total excavation project moved about 1.5 million cubic metres of material. Approximately 30,000 more cubic metres of rock were also used.
  • Ditches, dikes and temporary roads have been constructed on either side of the 6.5 kilometre (about four-mile) outlet.
  • The 95 pieces of heavy equipment used included excavators, bulldozers and rock trucks, one dredge, two Amphibex machines, one floating excavator, four barges, four tugs, two helicopters, 15 boats, 10 high-velocity pumps and 30 support vehicles.

Click here to view the latest aerial footage of Lake St. Martin Emergency Channel


Photo Gallery

Last few pieces of heavy equipment at inlet, Lake St. Martin in background   Last few pieces of heavy equipment at inlet, Lake St. Martin in background


Looking northeast, from inlet along the channel with the outlet in the distance and Lake Winnipeg   Outlet, looking southwest back to Lake St. Martin


Outlet, looking southwest back to Lake St. Martin   Buffalo marsh, Big Buffalo Lake, the channel and Lake St. Martin in the distance - southwest to Lake St. Martin
Share This